|
ISLAMABAD:
Ghazi Barotha Hydropower Project (GBHP) will start its full
power generation capacity of 1450MW by the end of next month
after functioning of fifth unit of 290MW.
'Pakistan Times' understands that the GBHP sources,
four units having equal
generation capacity of 290 MW each, have already been started
functioning and the last unit is due to start power generation
after completing test operation.
Perspective
The Ghazi Barotha Hydro Power Project had started functioning
early last year with first unit of 290MW and then three units
became operational one by one according to schedule.
The management of the project has started release of water in
its main Power Channel from February-16 after a gap of few
weeks having maintenance work of the water channel.
The water was being reserved in the Barrage since February-9.
The four power units were already functional producing
electricity of 1160 MW, while fifth and the last unit of this
project became operational on February 16, 2004 on
experimental basis and the full production will be started
from next month for achieving the target of 1450 MW
electricity of the project.
Power Channel
The power channel was closed on January-18 when the WAPDA
detected damages in the bed and sides of channel at certain
points and alleged the Ghazi Barotha Contractors, (GBC), a
consortium of national and multi-national construction firms,
of using substandard material.
The authorities of WAPDA, APHC and GBC agreed to jointly
determine the factual position through their experts by
suspending power generation.
Inquiry Report
The complete inquiry report along with its findings were
submitted to the Chairman WAPDA for further process of the
case and fixing responsibility after the inspection of the
power channel.
The Ghazi Barotha Contractors GBC, headed by Italian company
Impregelo, was directed by the WAPDA to carry out repair work
under defect liability period conditions effected till May-31
this year.
But, the GBC simply refused to accept the responsibility for
the damages and held the Pakistan Hydro Consultants (PHC)
responsible for designing a faulty structure of the project
despite the fact that the GBC had constructed the 52-km-long
and 40-ft-wide power channel.
Major n' Small Repairs
Meanwhile, the GBC under the defect liability period
conditions carried out seven major and a number of small
repairs in the power channel from zero to point 40.
The third biggest hydropower generation project of Ghazi
Barotha was completed in 2003 at the total cost of more than 2
billion US dollars.
It has 1450MW power generation capacity and was producing 1160
MW till January-18 with four units, each of 290 MW, operating
while the fifth one was expected to be made operational by the
end of March, 2004.
|